“92% of the Gas Interconnector Greece-Bulgaria, ICGB, is ready. The interconnector will be ready by the end of June, and will be tested with gas as of July,” Teodora Georgieva, Bulgarian Executive Officer of the company ICGB which is constructing the interconnector said for public service TV BNT.
"The 182-km. long linear part of the pipeline is ready. The pipes have been laid and covered, tests have been conducted. Besides Covid-19, the construction work has also been slowed down by delayed crane deliveries, but they too have now been tested. What remains is the construction of the gas stations in Stara Zagora in Bulgaria and in Komotini in Greece. The construction company is due to pay damages of EUR 90,000 per every day of delay after the beginning of 2022. The pipe’s capacity, which is 3 million cubic metres, and it has already been reserved," Teodora Georgieva said.
Bulgaria's Ministry of Transport has been working for years to develop Corridor No. 8, connecting the Adriatic with the Black Sea through Albania, North Macedonia and Bulgaria. Of the 1,220 km of railway line along the corridor, 747 km are on the..
A little less than a month ago, Minister of Finance Temenuzhka Petkova presented, in Brussels, the headway Bulgaria has made along the road to joining the Eurozone. There, she stated that with its prudent fiscal policy, the country had earned its..
From March 9 to 11, 2025, Inter Expo Center in Sofia plays host to the 41st edition of Holiday & SPA Expo. The event, organized with the support of the Bulgarian Ministry of Tourism, traditionally becomes a meeting point for leading experts,..
+359 2 9336 661