All principal construction work on the gas interconnector between Bulgaria and Greece via Komotini has been completed. Since mid-June the pipeline equipment has been filled and tested successfully with compressed natural gas. The gas pipeline, the seven valve stations, the two gas metering stations and the dispatch centre are technically viable, construction supervision has ascertained.
The Bulgarian-Greek company ICGB, which is the investor and future operator of the interconnector issued a statement denying allegations that the pipeline is unfinished. ICGB has submitted, to the Ministry of Regional Development and Public Works, a two-stage plan for the completion of the accompanying works.
The interconnector can be made operational in test mode at the end of August, ICGB says.
Bulgaria's Ministry of Transport has been working for years to develop Corridor No. 8, connecting the Adriatic with the Black Sea through Albania, North Macedonia and Bulgaria. Of the 1,220 km of railway line along the corridor, 747 km are on the..
A little less than a month ago, Minister of Finance Temenuzhka Petkova presented, in Brussels, the headway Bulgaria has made along the road to joining the Eurozone. There, she stated that with its prudent fiscal policy, the country had earned its..
From March 9 to 11, 2025, Inter Expo Center in Sofia plays host to the 41st edition of Holiday & SPA Expo. The event, organized with the support of the Bulgarian Ministry of Tourism, traditionally becomes a meeting point for leading experts,..
+359 2 9336 661