The planned annual repairs of Unit VI of Kozloduy NPP have been completed five days ahead of schedule. On November 1, at 1.41 am, it joined the country's energy system after an inspection and approval by the Nuclear Regulatory Agency.
The unit was stopped on September 29. For 31 days, the capacity of 1,000 megawatts was not part of the electricity market, which caused further rise of energy prices in Bulgaria.
Equipment maintenance has been performed and the unit has been refueled with fresh nuclear fuel. All the planned activities related to increasing the safety and ensuring the long-term operation of the unit have been carried out. The 5th nuclear power unit of Kozloduy is also operating at full capacity, the power plant's head Nasko Mihov said.
Bulgarian citizens in UK, who are accused of spying for Russia, planned to kidnap a Russian investigative journalist and take him off the island by boat, it became known at the last session of the trial at the Central Criminal Court..
It is too early to predict how the events in Syria would affect the war in Ukraine. This is what EU Defense Commissioner Andrius Kubilius said in a blitz interview with BNR - Horizont. The European Commissioner recalled that according..
On December 11 and 12, President Rumen Radev continues consultations with parliamentary groups in the 51st National Assembly before the first exploratory mandate for forming a government is handed out. Today, President Radev will meet with..
It is too early to predict how the events in Syria would affect the war in Ukraine. This is what EU Defense Commissioner Andrius..
Hundreds of miners protested outside the Council of Ministers while an extraordinary meeting of the National Council for Tripartite Cooperation was..
"I am addressing a question to the Prime Minister regarding information that on November 26 this year, a group of Bulgarian citizens was on trial in..
+359 2 9336 661